Where to start with a house extension

Almost everyone starts with the drawings. The two decisions that actually govern the project come before anybody draws anything.

Start with what you can spend and what the house has to do for you, in that order, and only then commission drawings. That sounds obvious and it is the step most often skipped. The usual sequence is the other way round: an architect is appointed because a neighbour used them, a design is produced that everybody likes, and the first real builder’s price arrives months later at a figure nobody expected. By that point the fees are spent and the choice is to cut the scheme apart or borrow more. Running a home project properly begins before that fork in the road, not after it.

So the honest answer to where you start is this. Write down what you want the finished house to do. Put a number against what you are willing to spend, including everything, not just the building work. Then have the two tested against each other by somebody who prices buildings for a living and is not going to earn a fee from the design. If the two do not meet, you want to know that in week one.

Settle the brief and the budget before the design

A brief is not a mood board. It is a short written list of what the house must deliver: how many bedrooms, whether the kitchen has to open onto the garden, whether you need a second bathroom, whether you can live in the house while the work happens. Half a page is enough. The value of writing it down is that it gives you something to measure the design against later, when the drawings are attractive and the price has gone up.

The budget needs the same treatment. One figure, written down, covering the building work, the professional fees, the statutory charges, the things you will buy yourself and a contingency. Most people carry a number in their head that covers the building work only, which is how a project that was going to cost one figure ends up costing considerably more without anybody doing anything wrong. We set out what belongs in that total in the costs that sit outside a builder’s quote.

With both written down, the question becomes answerable. Can this house do these things for this money. That is a question a quantity surveyor can price before you have a single drawing, and it is far cheaper to ask now.

Planning permission and building regulations are two different consents

These get used as if they were the same thing and they are not. Planning permission is about whether you may build the thing at all: its size, where it sits, how it looks, how it affects neighbours. Building regulations are about whether what you build is sound: structure, insulation, fire safety, drainage, ventilation. You can have planning permission and still fail building control, and plenty of work needs building regulations approval while needing no planning application at all.

Some extensions fall under permitted development and need no planning application. Others fall into the prior approval route. Planning Portal sets the prior approval band for larger single storey rear extensions at over four and up to eight metres beyond the rear wall for a detached house, and over three and up to six metres for any other house, with an application to the local planning authority and consultation with the neighbours who adjoin you. Local rules can also apply, which in London is common, so the position has to be checked for your address rather than assumed from a neighbour’s job.

Building regulations run on a separate track with its own body, its own application and its own certificate at the end. Who does what on that track is worth understanding early, and we go through it in building control on a home extension.

Get the order of appointments right

A typical extension needs a designer, usually an architect or an architectural technologist, and a structural engineer for the calculations wherever the structure is altered. Those are two different disciplines and the distinction matters, which is why we wrote whether you need an architect, an engineer or both.

You appoint and pay those consultants directly. That is deliberate, because it keeps their fees visible and their duty to you. Reltic does not design and does not carry design liability, so if you ask us to help, what we do is help you choose, agree scopes so that two consultants are not each assuming the other is covering something, and then keep their output moving in step with the builder.

The order that works is brief, budget test, design, consents, pricing, contract, build. Pricing before contract rather than after, because a price you have not interrogated is not a price. The sequence and the point at which somebody takes the job off your desk is set out in what a home project manager actually does.

What to have in front of you before you commit money

Before you pay a design fee, you want the brief and the budget written down, a note of the planning position for your address rather than for your street, and a view on whether the structure you have in mind is realistic. Before you pay a builder anything, you want a drawing set with revision numbers, a written specification covering the finishes and the fittings, and prices from more than one builder on the same documents.

That last point is where most private projects come apart. If each builder prices a different set of assumptions, the totals cannot be compared, and the lowest number usually belongs to whoever assumed least. We go through why that happens in how to read a builder’s quote.

You do not need all of it to have a first conversation. Send what exists, even if that is a sketch and a figure on the back of an envelope, and the first thing worth establishing is whether the two are anywhere near each other.

What this means for you

The expensive mistakes on a house extension are nearly all made in the first month, before any building work starts, and they are made by taking the steps in the wrong order. Design before budget. Builder before documents. Payment before a contract. None of those are dramatic at the time and all of them are hard to unwind once the scaffolding is up.

If you want the money tested before you commit to a design, that is a defined piece of work with a fixed fee, and you are free to stop there and use the report however you like. If you want somebody to run the whole sequence, that is home project management, and it is one person accountable from the first conversation to the day the certificates are handed over.

Not sure whether your budget and your brief meet?

Send us the sketch and the figure you have in mind. We will tell you in money, not in adjectives, how far apart they are.