Allow for professional fees, statutory charges, surveys and investigations, the items you buy yourself, the work needed where the new meets the old, and a contingency. On a private house project those sit outside the building contract, and a budget that covers only the builder’s figure will be short by a margin that matters. Part of what running a project on the client’s side involves is keeping a single total that includes all of it, rather than one number for the builder and a series of surprises around it.
None of these costs are hidden. They are simply not in the document people treat as the budget. Writing them down once, at the start, is the difference between a project that lands near its number and one that drifts for reasons nobody can point to.
Professional fees
The designer is the obvious one. An architect or architectural technologist for the drawings and the planning application, and in most cases a structural engineer for the calculations wherever the structure is altered. You appoint and pay both directly, which keeps their fees visible and their duty to you, and we explain the split between the two roles in whether you need an architect, an engineer or both.
Depending on the job there may be others: a party wall surveyor where the Party Wall etc. Act 1996 applies, a drainage survey, an asbestos survey on a house of the right age, an arboricultural report where a tree is close to the works, a planning consultant where the application is difficult. Each is modest on its own and they accumulate.
Our own fee sits in this group too. On a private project it is a fixed fee, agreed before the work starts, and we take no commission or referral fee from builders, architects or suppliers.
Statutory charges you pay directly
Building control charges are payable to whichever body you use, which GOV.UK describes as either your local authority’s building control department or a private registered building control approver. Planning application fees are separate again, and are set nationally rather than by your council.
Beyond those, a London job commonly carries a charge for building over or near a public sewer, which is agreed with the water company, and may carry fees for a crossover, a skip permit, a scaffolding licence or a parking suspension on the highway. Party wall matters carry their own costs where they apply.
These are paid directly by you rather than through the builder, so you see what each one costs. They are also not negotiable in the way a builder’s price is, which makes them a good place to be accurate early.
The things you buy yourself
On most private projects the kitchen, the sanitaryware, the tiles, the flooring, the wardrobes, the lighting fittings, the blinds and the garden are either excluded from the builder’s price or carried as an allowance in it. An allowance is not a price. It is a placeholder that will be adjusted to what you actually choose, and the adjustment is almost always upwards.
This is where a budget quietly fails. The building work lands on its figure and the finishes land well above the allowances, because the allowances were set before anybody had been to a showroom. Pricing the specification you actually want, rather than accepting the allowance, is the fix.
The same applies to anything you buy direct and expect the builder to install. Who orders it, who takes delivery, who stores it and who carries the risk if it arrives damaged all need settling in writing before the work starts, which is part of what agreeing the terms before the builder starts covers.
Where the new work meets the old
Extensions do not finish at the line on the drawing. The new opening into the existing house leaves decoration, flooring and sometimes heating to be made good beyond the extension itself. An extension that takes the kitchen may mean the old kitchen space becomes something else. A loft conversion changes the staircase and the landing below it.
Those items are frequently outside the quoted scope, and they are precisely the items you will notice when you move back in. Deciding now whether they are in the contract or in your own budget is better than deciding when the plaster is already up. Finding these gaps in a price before you sign is the subject of how to spot missing work in a builder’s quote.
Living costs belong in the same column where they apply. Rent if you move out, storage, a temporary kitchen, higher heating bills in a house that is open to the weather for a while.
Contingency, and VAT
A contingency is not a sign of a poorly planned project, it is the acknowledgement that an existing building will reveal something once it is opened up. On refurbishment and extension work the sensible provision is larger than on new build, and it should be yours to release rather than something the builder can draw on.
VAT needs checking for your own circumstances rather than assuming. Most domestic building work carries VAT at the standard rate, and certain categories of work are treated differently, so the position depends on the specific job. Confirm it against current HMRC guidance or with your accountant before the figure goes in the budget, and make sure every price you are comparing treats VAT the same way.
Put all of this in one schedule with the building contract as a single line. That sheet, kept up to date, is the only honest answer to the question of what the project costs.