Contractual provisions
The relevant events, the notice requirements and the assessment mechanism the contract provides, including any amendments made to them.
Time
Granting time is not agreeing to pay. The two are decided under different provisions, on different evidence, and settled together far too often.
The provisions that actually apply: which clause gives the right to time, for which events, and what it requires of you before it can be used.
A chronology built from records: what happened and when, taken from programmes, site records and correspondence rather than from recollection.
The notices, checked: whether they were served, when, and whether the contract makes late notice fatal or merely unhelpful.
A submission, not a complaint: the events, the entitlement and the preliminary assessment of impact, set out so the other side can follow and test it.
The problem
Most refused extensions are not refused because the delay did not happen. They are refused because the route to claiming it was not followed.
Notice periods are short and they start when the event becomes apparent, not when its consequences are finally understood.
A programme that was never agreed, never updated, or updated without saying what changed leaves nothing to measure delay against.
Concurrent delay turns a straightforward claim into an argument about which cause came first and which one mattered, and the answer depends on records that were either kept at the time or not kept at all.
What the work covers
A defined piece of work with a written deliverable and a clear scope. Fees are agreed individually based on the nature, complexity and scope of the matter.
The relevant events, the notice requirements and the assessment mechanism the contract provides, including any amendments made to them.
The baseline, the updates, the site records and the correspondence, and an honest view of what they do and do not support.
What happened, when it became apparent and what followed, set out in order and tied to the site records that show it.
Whether each required notice was served and in time, and what the contract says about the consequence if it was not.
The effect on completion as the records support it. Advanced forensic delay analysis is a separate discipline, outside this scope.
The claim assembled with its evidence attached, in a form that can be assessed rather than returned for more information.
An extension of time protects the programme. It does not, by itself, pay for anything.
Time and money run on separate provisions. An extension of time relieves liability for delay damages and resets the completion date. Recovering the cost of the delay is a separate claim, under separate clauses, with its own evidential requirements, and we prepare that separately as loss and expense.
This is commercial and contractual assessment, not legal advice, and not forensic delay analysis. Where a dispute turns on competing delay methodologies before a tribunal, that is specialist work and we will say so rather than present something thinner as though it were the same thing.
Questions
Not necessarily, and it depends entirely on the wording. Some contracts make notice a condition precedent, meaning entitlement is lost without it. Others treat late notice as a factor in assessment. That distinction is one of the first things we check.
No. It protects you from delay damages and moves the completion date. Payment for the cost of the delay is a separate claim under separate provisions, which is why the two are prepared separately.
No. We prepare the contractual claim: provisions, notices, chronology, records and a preliminary assessment of impact. Where a case needs a delay expert, you need one, and we will tell you that early.
Then the first job is establishing what can be measured against, which is sometimes a reconstructed sequence from site records. It is harder and it is honest to say so before the work starts rather than after.
Insights

Granting time is not agreeing to pay. The two are decided under different provisions and on different evidence, and...
Read the article
Every construction problem has a moment when it is cheap and a moment when it is not. The distance between them is...
Read the article
Nobody keeps records for the account they expect to be easy. The records that matter are made months before anybody...
Read the article