Reltic Construction Consultants Independent Commercial Advisory
Services
Project types
Who we work with
Projects Scenarios Insights Process About
Contact 020 3576 2851

Independent quantity surveyors across the UK

Cost decisions you can defend.

Quantity surveying and cost advice for contractors, developers, investors, lenders and homeowners. We act for one side of each project, from the first estimate to the final account.

Cover

Professional indemnity of five million pounds, evidenced.

One side

On every project we act for one party only. Never two sides of the same build.

Senior

The person who prices the work is the person who defends it.

Reach

Instructed across the United Kingdom, wherever needed.

Our standard

One standard on every report.

Every instruction is handled by a senior commercial lead. Nothing is passed down to a trainee. And nothing is sent to an offshore desk. The person who prices the work is the person who defends it when it is challenged.

Positions are traceable. Each quantity ties back to the model or the drawing it came from. Entitlement ties back to a clause. Valuations tie back to work genuinely in place, measured on site rather than assumed from a programme.

That traceability is the point. Consequently, a figure in a cost plan holds its shape when tender returns arrive, and a variation assessment holds its shape when a contractor disputes it. Where positions are not traceable, they are simply opinions with a number attached.

What we do

Where we take responsibility.

The capacity we act in is confirmed in writing before an instruction begins. If we already act for another party on the same project, we decline.

01

Cost planning and estimating

Know the real number before you commit
Cost planning and estimating

Budgets built on a rate per square metre fail quietly, then loudly at tender. We build the cost position from measured scope and test it against current market pricing before you commit to the scheme.

02

Quantities and take-off

Quantities the contractor cannot argue with
Quantities and take-off

Most arguments about money begin as disagreements about measurement. We produce quantities from the model and the drawings, recorded so that every figure can be traced back to the source it came from.

03

Tendering and procurement

The right builder on the right contract
Tendering and procurement

Procurement decides how much risk you keep and how much you pay somebody else to carry. We structure the route and the documents and the contract so that the bids you receive are genuinely comparable.

04

Cost control and variations

No surprises between valuation four and completion
Cost control and variations

Cost drifts in small increments, then arrives all at once. We value work in place each month, test every variation against the contract and forecast the outturn while there is still time to act on it.

05

Final accounts and disputes

Close the job without paying for someone else's mistake
Final accounts and disputes

Final accounts settle on evidence, and never on goodwill. We assemble the account, test the contractor's position line by line and support you through negotiation, mediation or adjudication if needed.

Specimen report

See what lands on your desk.

A complete monitoring report for a specimen scheme, written exactly as a live one would be. Nothing is redacted, because nothing in it is real. The project, the figures and the contractor are invented. The structure, the language and the level of detail are not.

Ask for it and you will know within two pages whether this is the standard you want on your scheme.

Sent as a PDF, usually the same working day.

Clients

Who we work with

Five kinds of client. One side per project.

01

Main contractors and subcontractors

Senior QS capacity without a full-time hire. Applications, variations and final accounts, prepared so they stand up when the other side checks.

02

Property developers

Cost certainty before the scheme is committed, and a defensible position later on, when the numbers are challenged by a contractor or a funder.

03

Funders and lenders

Independent appraisal, drawdown certification and monthly progress reporting, written to be read by a credit team, and not by another surveyor.

04

Private investors and family offices

Commercial oversight on schemes where the exposure is direct, the margin for error is small and nobody else is testing the numbers for you now.

05

Homeowners building or rebuilding

The builder’s price checked before you sign, the work valued each month as it is built, and the final account settled on evidence at the close.

How we work

How an engagement runs.

Continuity matters. The person who sets the cost plan is the person who defends the final account, through every step in between.

01

Brief and appraisal

We review the available information, the site, the programme and the budget, then set out exactly what our input will cover and what it will not.

02

Cost and quantity baseline

Quantities come off the model or the drawings. The cost plan is built from measured scope and tested against current market pricing rather than historic rates.

03

Procurement and contract

Tender documents go out on a basis that makes bids comparable. Returns are analysed line by line, and the contract is selected so risk sits where you intended.

04

Delivery control

Work in place is valued monthly. Variations are tested against the contract as they arise, and the outturn forecast is updated while there is still room to act on it.

05

Close out

The final account is assembled from the record built during delivery, not reconstructed afterwards. Where it is contested, we hold the position.

Spend against the facility
Cost accrues as a curve, funding arrives in tranches. The gap between them is what a drawdown cycle answers every period.
Cumulative spend against facility drawn Two lines over the construction programme. Cumulative cost rises as a smooth S-curve, slow at the start, steep through the middle, flattening towards practical completion. Facility drawn rises in steps as each tranche is certified, staying just above the cost curve. Facility drawn Cumulative cost Start on site Practical completion Vertical axis: cumulative value. Schematic shape, no scheme data.
Cumulative cost Facility drawn
Acting for a lender? The drawdown cycle runs to a different rhythm. See the monitoring cycle
What it costs to resolve a change, later
The records that settle a variation are made on site in the weeks around it. Their useful life is short, and the price of the argument grows as they fade.
Relative cost of resolving a change over time Five bars rising from left to right. Resolving a change in the month it happens is the smallest bar. Cost rises at three months, six months and twelve months, and is largest once the matter reaches the final account. Same month 3 months 6 months 12 months Final account Vertical axis: relative cost to resolve. Schematic, not measured data.
Step 04 exists for this reason. A change closed in the month it happens costs what it should. The same change closed at the end is a negotiation.

Scenarios

Situations that bring clients in

Most instructions begin at the same three points. None of them are comfortable.

01Cost exposure

The budget held through design, then moved twice in six weeks once the packages came back.

We rebuilt the cost position from measured scope, identified where the drift had entered and set out what it would take to recover it. The board saw a single number rather than a moving one.

Read this scenario
02Contract position

Both parties read the same clause and arrived at opposite conclusions about who carried the cost.

We tested the entitlement against the contract and the record, then held that position through negotiation. Where the client was wrong, we said so early rather than late.

Read this scenario
03Incomplete design

Packages went out to tender while the design was still moving, and the returns priced the gaps as risk.

We identified what was genuinely undefined, priced the exposure openly and kept it visible in the cost plan rather than buried in a contingency line.

Read this scenario

Questions

Frequently asked.

Do you work for contractors?

Yes. We prepare applications for payment, variation accounts and final accounts for main contractors and subcontractors. On any one project we act for one party only, so we never act for a contractor and its client on the same build.

I am a homeowner. Can you check my builder’s quote?

Yes. That is one of the most useful moments to bring us in, because the price is still open to change.

Is my project too small for you?

Tell us what it is. If it is not work we should take, we will say so and point you somewhere sensible.

How do you charge?

It depends on what the engagement is. Full lifecycle commercial appointments are usually percentage based against project value. Defined pieces of work, an appraisal or a set of tender documents, are quoted as a fixed sum. Expert and dispute work runs at a day rate, and ongoing oversight for investors is handled on a monthly retainer. The basis is agreed and written down before anything begins.

What does independence actually mean here?

We hold no design fees and no software licences to sell. On every project we act for one party only: the client, the contractor or the lender. We never act for two sides of the same build. If a conflict exists, you hear about it before the instruction is accepted.

When is the right time to bring you in?

Feasibility, before the budget hardens into a commitment. That said, most instructions arrive later than that. Joining at tender, mid delivery or at final account still works, and the position can still be recovered. Earlier simply gives more room to shape the outcome rather than defend it.

Do you work for lenders as well as developers?

Yes, but never on the same scheme. Monitoring instructions run through initial appraisal, drawdown certification, monthly reporting and final account verification. Where two parties approach us about one project, we take the first instruction and decline the second.

What size of project do you take on?

The work suits schemes where the commercial position is genuinely complex rather than simply large. Residential development, mixed use, refurbishment and phased schemes are the usual territory. On every one of them the instruction stays with the same senior commercial lead from feasibility to final account, with no handover to a junior once the fee is agreed.

Do you need a BIM model to work?

No. Where a model exists we measure from it and audit what it contains. Wherever it does not, we measure from drawings. The model is a method rather than a requirement, and the standard of the output does not change either way.

Do you work across the whole of the UK?

Yes. Reltic is not built around a single office. Site attendance is set by the project and the valuation cycle, wherever the scheme sits.

Do you work in London?

Yes. Recent instructions include a six storey residential scheme in East London and five new build houses in Twickenham, alongside a residential block in Manchester and an industrial unit in Liverpool. Site attendance is set by the project and the valuation cycle, wherever the scheme sits.

Get in touch

Talk to us before you commit

Tell us what the scheme is, where it has reached and what is currently uncertain. If it is not work we should take, we will say so and point you somewhere sensible.

Telephone
Postal address
Office 676, 60 Tottenham Court Road, London W1T 2EW

We reply to every enquiry within one working day.

By sending this enquiry you agree to us using your details to respond to it. Nothing is shared with third parties. See our privacy policy.