Building control on a home extension, and who does what

Building regulations approval is a separate consent from planning permission, with a different body, a different process and a different certificate.

The short version. You choose the building control body and the charges are payable by you directly. The duty to notify sits with the owner or the person carrying out the work, so it has to be agreed in writing whether you or the builder makes the submission and calls the inspections. The body inspects, decides whether the work complies and issues the certificate at the end. None of those decisions belong to your builder, your architect or to us. Where a project manager on your side helps is in making sure the responsibility is allocated, the visits line up with the programme and the paperwork exists when you need it.

First, the distinction that causes the most confusion. Planning permission is about whether you may build it: size, siting, appearance, effect on neighbours. Building regulations are about whether what you build is sound: structure, fire, insulation, drainage, ventilation. They are separate consents. Having one does not give you the other, and plenty of work needs building regulations approval while needing no planning application at all.

Who you apply to

GOV.UK puts the choice plainly: you can either use your local authority’s building control department or a private registered building control approver. Both operate under the same building regulations. The older term approved inspector has given way to registered building control approver, so if an older document in your project file uses it, that is what it means.

A separate route exists for higher risk buildings, which go to the Building Safety Regulator. A house extension or a loft conversion on a single family home does not fall into that category, so for a normal domestic project the choice is between your council and a registered approver.

The charges are payable directly by you, which is why they sit outside our fee and outside the builder’s price. Alongside them sit the planning application fee where one applies, and any charge for building over or near a public sewer. Those and the rest of the costs around the contract are listed in the costs that sit outside a builder’s quote.

Which route, and what you get at the end of it

There are two ways in. A full plans application means your drawings and calculations are checked before the work starts. GOV.UK calls it the most thorough option and says you can expect a decision within five weeks, or two months with your consent. You end up with a formal decision on the plans, which is worth having when you come to sell or remortgage.

A building notice is for smaller projects. It does not give you formal approval of the plans, and work can start two days after the notice has been submitted. It suits simple work where nothing unusual is being attempted. On a job with a significant structural element, having the design checked first is generally the better position, because a problem found on paper is far cheaper than the same problem found once the steel is in.

At the end, GOV.UK says you will usually get a completion certificate within eight weeks of completion of the building work, as long as it complies. That certificate is the document a buyer’s solicitor will ask for. Without building control approval you will not have the certificates of compliance when you want to sell the house, which is the practical reason none of this is optional paperwork.

Who notifies, and why that has to be agreed

The duty to notify building control at the required stages rests with the owner or the person carrying out the work. In practice the builder usually makes the calls, because the builder knows when the trench is open. But usually is not an arrangement, and the consequence of nobody calling falls on you, because it is your house and your certificate.

Councils are explicit about the consequence. One states that it is unable to issue a completion certificate if it has not been called out for the relevant inspections. That is the whole risk in a sentence: work that was perfectly well built can be hard to certify simply because it was covered up before anybody saw it.

So the arrangement goes in writing before the work starts. Who submits the application. Who calls each inspection, and how far in advance. Who sends you the confirmation afterwards. Who is responsible if a stage is missed. It is three lines in the paperwork and it removes the argument entirely.

What to keep, as you go

Keep a simple log with the date each inspection was called, the date it happened and what the body said. Keep every email and every inspection record. Keep the approved drawings and the structural calculations, with revisions, because the version that was checked is the version that matters.

At handover you are collecting a set of documents, not just a certificate. The building control completion certificate. A certificate from a scheme registered electrician for the electrical work. Documentation from a Gas Safe registered installer where there is gas work. For windows, ask which applies to your job, because replacement windows are often registered under a scheme such as FENSA while windows in a new extension are usually covered by the building control application for the extension itself.

Add the warranties and the manuals for anything installed, and the as built drawings where the work differed from the design. We go through assembling that set in what to check before the final payment.

What this means for you

Treat building control as a track that runs alongside the build with its own dates and its own paperwork, rather than as a formality at the end. Choose the body, decide the route, allocate the notification duty in writing, and keep the records as you go rather than assembling them in a panic at completion.

Our role in this is coordination. We help establish who is responsible for the submissions, line the inspection dates up with the works programme, and collect the documents you will need at handover. The decisions and the certificates themselves remain with the appropriate building control body, and the charges remain payable by you directly.

Not clear who is calling the inspections on your job?

We allocate the notification duty in writing, build the visits into the programme and collect the handover documents as the work proceeds.