Which building control inspections to plan for

The stages are predictable. What catches people out is the notice each one needs and the cost of covering work up before it has been seen.

On a typical house extension the stages are commencement, excavation for the foundations, the foundation concrete, the oversite, the damp proof course, the drainage before it is covered, and a completion inspection at the end. Councils do publish their own lists and they are not identical, and the notice each wants varies from twenty four hours to two working days depending on the body, so the only reliable schedule is the one your own building control body gives you. Getting that list at the start and putting it on the programme is a small piece of having the build run for you that saves a disproportionate amount of trouble.

The reason the detail matters is that several of these stages are only inspectable for a short window. A foundation trench can be looked at before the concrete goes in and not afterwards. Drainage can be seen before it is backfilled. Miss the window and the conversation turns into opening work up again, at somebody’s cost.

The stages, in the order they arrive

Commencement comes first, notifying the body that work is starting. Then the foundation excavation, inspected with the trench open so that the ground conditions and the depth can be seen. Then the foundation concrete, before anything is built off it or backfilled against it.

After that the oversite, the damp proof course where it is formed, and the drainage, which needs seeing while the runs are still exposed and usually needs testing. Structural elements get looked at as they go in, which on a domestic extension usually means the beam over the new opening and its bearings. Insulation and the build up of floors, walls and roof are checked before they are closed in.

The completion inspection comes at the end and triggers the certificate. GOV.UK says you will usually get a completion certificate within eight weeks of completion of the building work, as long as it complies.

Notice periods, and why you cannot borrow somebody else's

Published requirements differ. One council asks for twenty four hours notice of each stage, another sets a minimum of two days for the commencement notice, another asks for at least two working days before you intend to start. The stages themselves also vary slightly, with some bodies listing oversite and occupation separately and others combining stages.

The practical consequence is that a schedule taken from a neighbour’s project or from a general article is not good enough. Ask your body for its own notification schedule when you make the application, and put the stages on the programme with the notice period attached to each.

Then agree who makes the calls. The duty to notify rests with the owner or the person carrying out the work, so it has to be settled in writing whether that is you or the builder. That allocation is part of what we cover in building control, and who does what.

What happens when a stage is missed

The honest answer is that it depends on what was covered and whether the body is prepared to accept other evidence. Sometimes photographs taken at the time, a record from the engineer or a sample opening up will satisfy them. Sometimes the work has to be exposed again.

Hypothetical example, to show the shape of the problem rather than any real project. Suppose the drainage is backfilled on a Friday without being called in, and the body will only certify it after seeing it. Somebody now has to dig it out, have it inspected and backfill again, which costs money and a week. If the builder was contractually responsible for calling the inspection, that cost is a matter for the builder. If nobody was clearly responsible, you will be paying for at least part of it. The figures are illustrative and no amount is implied.

That is the whole argument for writing the responsibility down. The work in question may be perfectly sound. The problem is evidential, and evidence is cheap to create at the time and expensive to recreate later.

The record to keep while it is happening

Keep a one page log: stage, date called, date inspected, outcome, and a reference to the email or the portal entry. Keep the photographs the builder takes of trenches, reinforcement, insulation and drainage before each is covered. Those photographs are worth asking for as a standing requirement rather than after the event.

Keep the correspondence with the body separate from the general project email. At completion you want to be able to show the sequence without searching, and when you sell the house the file is what the buyer’s solicitor will ask about.

If the work changes as it proceeds, which on an existing building it usually does, make sure the revised design reaches the body as well as the builder. An approval relates to what was submitted, so a change that nobody told them about is a gap in the trail.

What this means for you

None of this requires you to understand the technical standards. It requires somebody to hold a list, make a telephone call at the right time and keep the replies. That is administration rather than expertise, which is precisely why it gets forgotten on a busy site.

Get the notification schedule from your own body, put every stage on the programme with its notice period, agree in writing who calls each one, and insist on photographs before anything is covered up. That is most of the risk managed, and none of it is technically difficult.

Where we are running the project, this sits with us: the visits go on the programme, the calls are tracked against it, and the records are collected as the work proceeds rather than reconstructed at the end. The inspections and the certificate remain the building control body’s own decisions.

Want the inspection dates built into the programme?

We take the schedule from your building control body, put it on the programme and track every call against it.