How to coordinate your architect, engineer and builder

Three capable people working to three different versions of the same project is the most common reason a house build stalls.

Coordination is mostly about three things: one register of current drawings, one list of decisions still owed, and one programme that the design, the consents and the construction all sit on. Get those three in place and most of the friction disappears. Without them, the architect is working on a revision the builder has never seen, the engineer is waiting on a dimension nobody has asked for, and you are being asked to choose tiles while a steel is holding up the job. Independent support through the build exists largely to hold those three documents and to chase the things on them.

The reason this falls to somebody is that none of the three parties is naturally placed to do it. The architect is not on site every week. The engineer is engaged for a defined piece of work. The builder has an interest in the answer, so asking the builder to manage the flow of information to the builder is not a control.

Keep one register of what is current

Every drawing has a number and a revision. The single most common cause of abortive work on a house project is somebody building to a superseded sheet, usually because a revised drawing was emailed to one person and not to the others. A register that lists each drawing, its current revision, its date and who has it solves a problem that is tedious rather than difficult.

The same applies to the specification and to the structural calculations. If the engineer changes a beam size, that change has to reach the builder who is ordering the steel, the designer whose detail sits around it and the building control body that is checking it. One of those three is usually missed.

Ask for drawings to be issued to everybody at once, with the revision visible in the file name. It sounds bureaucratic until the first time somebody builds the wrong opening width.

Hold a list of decisions and the date each is needed by

Builders rarely stop because of a shortage of work. They stop because of a shortage of answers. Which way the door swings, where the sockets go, whether the floor is engineered oak or tile, whether the rooflight is the one in the specification or the one you saw somewhere else. Each of those has a date by which it has to be settled or it holds something up.

The practical tool is a short schedule of outstanding decisions with a date against each, reviewed weekly. It converts a vague sense of being chased into a list you can work through in an evening. It also protects you, because when a decision is given on time and the work still slips, the reason lies elsewhere.

Decisions given verbally on site are the ones that cause arguments later. If a choice is made during a site visit, it needs confirming in writing the same day, which is the same discipline as agreeing the price of a change before work starts.

Put the consents on the same programme as the work

Planning permission and building regulations approval are separate consents with separate timetables, and both have to be reflected in the programme rather than assumed. On the building regulations side, GOV.UK describes the full plans route as the most thorough option, with a decision expected within five weeks, or two months with your consent. The building notice route is for smaller projects, gives no formal approval, and allows work to start two days after the notice is submitted.

Which route you use changes how much checking happens before anybody builds, which in turn changes how much risk sits on site. On a job where the structure is unusual, having the plans checked in advance is worth the wait. We go through the roles in building control, and who does what.

Inspection visits then have to be built into the programme rather than remembered on the day. The notice each body wants before a visit varies, and the stages are not identical everywhere, so the schedule has to come from your own body. That sequence is in the inspections to plan for.

Decide who speaks to whom, and write it down

Three rules are usually enough. Instructions to the builder come from one place. Questions about design go to the designer and are copied to whoever is coordinating. Anything that affects cost or time is priced and agreed before it is built, not after.

The failure mode without those rules is familiar. A builder asks you a question on site, you give a sensible answer, the answer conflicts with the drawing, and six weeks later nobody can say who authorised it. On a private job you are both the client and the person standing there, which makes this harder than it sounds.

Agreeing in writing who may issue instructions is part of settling the terms before work starts, which we cover in what to agree before the builder starts.

What this means for you

You appoint the architect and the engineer in accordance with what the project needs, and design and calculations remain with them throughout. Coordination is a separate job: keeping the information current, the decisions listed, the consents on the programme and the instructions coming from one place.

If you already have a team, we work with them rather than replacing them. If you do not, we can help you choose and then agree the scopes so that nothing sits in the gap between two appointments. Either way the weekly discipline is the same: a site meeting, a written report, and a list of what is owed and by when.