Insights for homeowners

What to check before the final payment

The last payment is the last leverage. Everything you want from the builder has to be in your hands before it leaves yours.

Four things before the money moves. The account reconciles: contract sum, plus agreed changes, less omissions, less retention. The certificates and documents are physically in your possession. The defects list is closed or the retention still covers what is left. And the final figure has been agreed in writing as final. That reconciliation is routine work for a quantity surveyor acting for the homeowner and it is the step most often skipped, because by this stage everybody wants the job to be over.

It helps to remember what the final payment is. It is not a formality at the end of a long process, it is the moment you give up the only practical means you have of getting anything else done. Whatever is unresolved when it leaves is likely to stay unresolved.

Reconcile the account rather than reading the invoice

Start from the contract sum and work forwards. Add each agreed change at its agreed value. Deduct each omission. Deduct everything already paid. Deduct the retention. The figure you arrive at is what is due, and if the builder’s number differs, the difference is where the conversation belongs.

Check that every change on the account has an instruction behind it and was agreed before the work was done. Anything that appears for the first time on the final account deserves the same four questions as any other extra, set out in what to check when a builder charges for extra work.

Watch for work claimed twice, for omitted work that has not been credited, and for provisional items and allowances that have been charged at more than the work actually done. On domestic accounts these are usually errors rather than anything worse, and they are still your money.

Collect the documents before you pay, not after

The building control completion certificate is the one that matters most, because it is what a buyer’s solicitor will ask for. GOV.UK says you will usually get a completion certificate within eight weeks of completion of the building work, as long as it complies, so if the inspections have not all been carried out this is the point at which you find out.

Then the trade documents. A certificate from a scheme registered electrician for the electrical work. Documentation from a Gas Safe registered installer for any gas work. For windows, ask which record applies to your job, because replacement windows are often registered under a scheme such as FENSA while windows in a new extension are usually covered by the building control application for the extension itself.

After that: structural calculations and the approved drawings with revisions, as built information where the work differed from the design, manufacturers’ warranties and guarantees, manuals and commissioning records for the boiler and any mechanical ventilation, and any insurance backed guarantee that was promised. Who was responsible for obtaining each of these should have been settled at the start, as in building control, and who does what.

Close the defects list, or keep the money that covers it

Walk the job again against the numbered list and sign items off individually. Items you have not seen are not closed. If a handful remain, you have two options: hold enough money to cover them, or agree a dated programme for the remaining work in writing with the retention still in place until it is done.

Do not accept a general assurance in exchange for the final payment. Once the money has gone, the return visit depends entirely on goodwill, and goodwill is in short supply after a long job. The method for compiling and running the list is in putting together a snagging list before handover.

Keep the retention structure intact to the end. Part at completion, part after the defects period, and the final part only when you have been round the house once more. Diarise that date, because the defects period expires quietly.

Get the figure agreed as final, in writing

Ask for written confirmation that the agreed figure is the full and final amount due under the contract, including all changes, and that no further claims will follow. Then pay it. A final account that is agreed in an email is worth more than one that is assumed from silence.

Check the invoice itself. The correct legal entity, the right project address, VAT treated consistently with the way it was treated in the contract and in every previous application, and the payment details the same as those you have used throughout. If the bank details have changed at the final payment, confirm them by telephone on a number you already hold before transferring anything.

Keep the whole file together afterwards: contract, drawings, specification, change schedule, every valuation, the certificates and the correspondence. That is the pack you will need when you sell the house, and reassembling it years later is far harder than keeping it now.

What this means for you

Give yourself a week between agreeing the figure and paying it. Nothing is lost by the delay, and a week is long enough to notice the certificate that never arrived and the two items on the list that were never actually done.

Do not treat the final payment as administration. Reconcile the account from the contract sum forwards, get every certificate and warranty physically in hand, close the defects list item by item or keep money against it, and obtain written confirmation that the figure is final.

Where we have run the job, the account has been kept current throughout, so closing it is a reconciliation rather than an archaeology exercise. If you have reached this point without that, the account can still be reconstructed and tested, and it is usually worth doing before the last payment rather than after.

This article is general information about running a building project, not legal advice on your contract.