Bring whatever exists and the figure you are willing to spend. That is the short answer. You do not need a tender pack, a finished design or a planning decision in order to have a useful first conversation about having your build run for you. What you do need is to be straight about the budget, because every piece of advice you get afterwards depends on it, and a number chosen to sound sensible will send the whole project in the wrong direction.
The purpose of a first meeting is not to admire the scheme. It is to establish three things: what you are trying to build, whether the money and the scheme are in the same place, and what the next sensible step is. An hour spent on that is worth more than three months of drawings produced against an untested figure.
What to bring, in order of usefulness
The budget first. One number, everything in, and the part of it you would rather not spend. Then whatever drawings exist, even if they are hand sketches, with any revision numbers or dates visible. Then any prices you have already been given, in full, including the covering emails, because the exclusions in a quote are usually in the words around the figure rather than in the figure.
After that, the paperwork about the property. The planning position if you know it, any pre application advice, the deeds or title plan if a boundary is involved, and any correspondence with neighbours. If the house is in a conservation area or is listed, say so at the start, because it changes the answer to almost every other question.
Finally, the constraints that are about you rather than the building. Whether you can move out, whether there is a date you have to be finished by, whether the money arrives in stages, whether you are working full time and cannot be on site. Those shape the procurement route as much as the drawings do, and we deal with the last one in keeping a renovation moving while working full time.
What you do not need yet
You do not need a full specification, a structural scheme, a programme or a contract. You do not need to have chosen a builder, and if you have already chosen one it is better to say so plainly than to present their price as a neutral benchmark. You do not need to have decided the kitchen.
You also do not need to have tidied the project up. A half finished design, three quotes that do not agree and a budget that has already moved twice is the normal starting position, not an embarrassing one. The thing that wastes a meeting is a version of the project that has been smoothed over, because the advice then addresses a project that does not exist.
The questions worth asking
Ask whether the scheme is affordable at the figure you have given, and ask for the answer in money. A straight answer sounds like a range with the assumptions stated, not like encouragement. Ask what is missing from the information you have brought, because that list is the real agenda for the next month.
Ask who is going to be doing the work on your project and who you will be speaking to in month five. Ask how the fee is calculated, whether it is fixed, and what would make it change. Ask whether the person you are talking to takes any payment from builders, architects or suppliers, because that decides whether a recommendation is worth anything.
Then ask what the next step costs and what you get for it. A first piece of work should be definable: a written view on the prices you hold, or a benchmark estimate against your brief, with a fixed fee and a report you can act on without committing to anything further.
What you should walk away with
Three things. A view on whether the budget and the brief are compatible. A list of the documents that have to exist before anybody can be asked for a firm price. And a clear next step with a price against it.
You should also walk away knowing what the engagement would not cover. Design sits with your architect, structural calculations sit with your engineer, and decisions and certificates under the building regulations sit with your building control body. Anybody who implies that one appointment covers all of that is describing something that does not exist.
If the answer is that your scheme does not need the help, that is a legitimate outcome of a first meeting. It is cheaper to hear it in an hour than to discover it in month four.
What this means for you
One habit is worth adopting from the first meeting onwards. Whatever is agreed, whether it is a figure, a date or a decision about the scheme, confirm it in a short email afterwards. On a project that runs for months, the written trail is what makes the early conversations usable later, and it costs nothing to start it on day one.
Preparation for a first meeting is mostly honesty rather than paperwork. The budget you are actually willing to spend, the drawings as they really are, the prices in full rather than summarised, and the constraints you would rather not mention. On that basis an hour can genuinely change the shape of the project.
Send the documents ahead if you can, so the hour is spent on conclusions rather than on reading. If you are not sure what to send, send everything and let us sort out what matters.
Have a pile of drawings and quotes and no view on them?
Send what exists, however rough. We will come back with what we make of it and what the next step would cost.