How to agree a payment schedule with your builder

Pay for work that is standing on site, in stages you can measure, and never ahead of the building.

Tie each payment to a stage that can be looked at and agreed, hold a retention until the defects are dealt with, and write the whole timetable into the contract before the first payment is made. The reason to be precise about this on a private job is that your payment timetable comes from your contract rather than from the general statutory scheme. Section 106 of the Housing Grants, Construction and Regeneration Act 1996 takes contracts with a residential occupier outside the statutory payment and adjudication provisions, so what the contract says is what governs. That is one of the first things an independent surveyor on your side looks at, because a vague schedule is very hard to argue with later.

The principle is simple and it is the one most often broken. Money should follow work. If payment four falls due in week twelve regardless of what is built, the schedule is a finance arrangement rather than a payment mechanism, and by month three you may be materially ahead of the work without anybody having done anything wrong.

Make each stage something you can stand in front of

First fix sounds precise until half of it is done and the invoice arrives anyway. Words like structure complete, plastered, nearly finished and watertight are all capable of two honest readings. A stage that cannot be verified on a walk round is a stage that will be argued about.

So write stages that describe a physical state. Foundations complete and inspected. Walls up to and including the beam over the opening, with the beam in place. Roof structure, membrane and covering complete. Windows installed. Plastering complete to the new rooms. Each of those can be looked at and either is or is not true.

Tie them to the inspection points where you can, because those are dated and recorded by somebody independent of both of you. The sequence of visits is in the building control inspections to plan for.

Decide between stage payments and monthly valuations

Stage payments suit a short job with a clear sequence. You agree a value against each stage at the start, the stage is reached, the payment is made. The weakness is that a stage is binary, so a stage that is nearly complete creates pressure to pay anyway.

Monthly valuation suits a longer or more complicated job. Instead of fixed stages, the work actually in place is measured each month and paid for. It is more work to administer and it is more accurate, and it means a part completed element is paid at its part value rather than all or nothing. How that assessment is made is set out in paying for work actually in place.

Whichever you choose, say in the contract how the figure is arrived at, who checks it, how long you have to check it and when payment falls due after that. Those four points are what turn a schedule into a mechanism.

Hold a retention, and write down how it is released

A retention is a percentage held back from each payment, released in part at completion and in part after the defects period has run. It is the only practical leverage you have once the builder has left, and on private jobs it is very often either absent from the contract or released early by inattention.

Write down the percentage, what happens to it at completion, how long the defects period runs, and what has to happen before the final part is paid. Then diarise the release date, because the date passes quietly and the money tends to be paid out simply because somebody asked. The mechanism and the way it fails is covered in defects, retention and the last five per cent.

Hypothetical example, for illustration only. On a contract sum of £200,000 a retention of three per cent is £6,000, with half released at completion and half after the defects period. That remaining £3,000 is what gets a builder to come back for the small items in month ten. The figures are illustrative and not a recommendation of any particular percentage.

What has to be in the document

The contract sum and what it includes. The payment stages or the valuation cycle, with the figure or the method against each. How a change is priced and agreed, which we deal with in agreeing the price of a change before work starts. The dates for starting and finishing. The retention and its release. The defects period. Who may issue instructions.

JCT publishes contracts written for home owners, including a version for use where a consultant has been appointed to oversee the work, and those forms already contain a payment mechanism, a defects period and a change procedure. Starting from a published form written for private clients is almost always better than an exchange of emails, because the awkward questions have already been thought about by somebody else.

Keep the priced schedule as an appendix to the contract. When a payment application arrives, you then have something to measure it against, rather than a total to accept or dispute.

What this means for you

Write the schedule before you pay anything, make every stage physically verifiable, decide who checks each application and how long you have, hold a retention and diarise its release. None of that is adversarial. It simply means both sides know what happens next, which is what keeps a job civil.

Where we are involved on the money, every application is checked against the work standing on site before you release anything, and the account is kept running through the build so the final figure is not a surprise. If you would rather have the schedule set up properly and then run it yourself, that is a reasonable place to stop.

This article is general information about running a building project, not legal advice on your contract.