Residential development

Twenty four apartments, single block

One block, three apartment types repeated through it, and a set of communal areas that had to be apportioned across all twenty four. The building was not the difficult part. Keeping the cost consistent between types was.

The scheme

Repetition only helps if it holds

A multi-unit block looks like a cost planner's easy job. One type, priced once, multiplied out. In practice the types drift: a different window here, a wider corridor there, a services riser that only appears on two floors.

Every one of those differences is small. Multiplied across twenty four units, small stops being the right word for it.

At a glance

The commercial facts

Everything we publish about a scheme, and nothing that identifies anybody.

Scheme
Twenty four one, two and three bedroom apartments
Location
Manchester, Greater Manchester
Value
circa £5m
Stage
Pre-construction
Our role
Quantities, scope and cost review

Our part in it

What we were asked to do

Rebuild the quantities from the drawings rather than accept the schedule as given, so each apartment type could be priced on its own basis and compared against the others.

Test the scope for what had been left between packages, particularly around the communal areas, where responsibility is easiest to assume and hardest to find later.

Set out the cost position in a form the client could take to a board and defend, with each figure traceable back to the drawing it came from.

The scheme

What a job of this kind looks like

Brick and metal clad facade of the completed residential block in Manchester
Entrance lobby of the Manchester residential block with terrazzo floor and lift
Completed apartment interior in Manchester with full height glazing and city view
Concrete frame and scaffolding of the Manchester residential block during construction