A single use building on a large plot, where the frame is the simple part and the yard, the drainage and the access are where the money quietly goes.

The scheme

Simple building, difficult site

A portal frame shed is one of the most predictable structures to price. Steel, cladding, slab, roof. The elements are few and the rates are well established.

What is not predictable is everything outside the walls. Yard construction to take articulated vehicles, drainage across a large impermeable area, service connections, fencing and gates. On a scheme like this the external works can carry more cost than the building, and they are the part most often carried as a single allowance.

At a glance

The commercial facts

Everything we publish about a scheme, and nothing that identifies anybody.

Scheme
New industrial and logistics facility with external works
Location
Liverpool, Merseyside
Value
£1m to £5m
Stage
Pre-construction
Our role
Cost plan, tender documents and bid analysis

Our part in it

What we were asked to do

Produce the cost plan with the external works measured as their own elements rather than sitting as one figure at the bottom of the page.

Set out the tender documentation so that every contractor priced the same scope, with the ground and drainage assumptions stated rather than left to each bidder.

Analyse the returns line by line, normalising the qualifications so the comparison between bids meant something.

The scheme

What a job of this kind looks like

Completed industrial unit in Liverpool with glazed office frontage and concrete yard
Loading dock elevation of the completed Liverpool industrial unit
Structural steel frame of the Liverpool industrial unit during erection, with a mobile crane on site
Completed access road and drainage serving the Liverpool industrial unit
Detail of profiled metal roof sheeting meeting brickwork on the Liverpool unit