Reltic Construction Consultants Independent Commercial Advisory
Services
Project types
Who we work with
Projects Scenarios Insights Process About
Contact 020 3576 2851
Appraisal figures and site plans laid out on a desk

Insights on development management

How much should you pay for a development site

The asking price is an opinion. The residual land value is the only figure that tells you what the site is worth to you.

An investor buying a development site is not buying land. They are buying the right to build something and sell or hold it. That means the land has a value to you that has almost nothing to do with the asking price and everything to do with what the finished scheme is worth and what it costs to get there. Working that out is the first job in site sourcing and appraisal, and it is the job most often done with a rule of thumb.

The method is called the residual land value. You start at the end, with the value of the completed development, take off everything it costs to build and sell, take off the profit the scheme has to make, and whatever is left is what you can afford to pay for the land. Done properly it gives you a ceiling price and a reason to walk away. Done loosely it gives you a number that justifies whatever you already wanted to pay.

Start at the end, not at the asking price

The sequence matters. If you begin with the price the agent has quoted and work forwards, every other figure in the appraisal becomes a variable you adjust until the deal works. Build cost drifts down, sales values drift up, contingency disappears, and the appraisal tells you what you hoped rather than what is there.

Working backwards removes that temptation. The value of the finished scheme and the cost of building it are both external facts that you can test against evidence. The land price is the only genuine unknown, so it should be the output of the calculation and not an input to it.

This is also the version a funder will want to see. A lender reading an appraisal that starts with the land price can tell immediately that the numbers have been fitted to a decision already taken.

Gross development value needs evidence, not optimism

The value of the completed scheme is the largest single figure in the appraisal and a small error in it moves the land price a long way. It should come from comparable evidence for the right unit type, the right size and the right location, and from an agent who is willing to put the figure in writing rather than in conversation.

Two mistakes recur. The first is valuing the scheme at the top of the range because the specification will be better than the comparables, when the specification has not been designed yet. The second is assuming every unit sells at the same rate, when in practice the last units in a block often take longer and sell for less.

If the scheme is to be held rather than sold, the same discipline applies to the investment value: achievable rents, a yield that reflects the actual covenant and location, and an allowance for the time it takes to let.

The cost side is wider than the build contract

The construction contract is the obvious cost and usually the only one carried at any accuracy in an early appraisal. Around it sit professional fees, surveys and investigations, planning application costs and obligations, utility connections and diversions, building control, warranties, insurances, finance costs, sales and letting agency, legal fees on both purchase and sale, and stamp duty on the land.

None of those are optional and together they are not a rounding error. We go through them one by one in the five costs first-time developers leave out, because the pattern is consistent.

The build figure itself should come from measurement rather than a rate. Where drawings do not yet exist, an elemental estimate built for your scheme on your site is a far better starting point than an average rate taken from a published source, and we explain why in feasibility and cost planning.

Profit is an input, not what happens to be left

The profit the scheme needs is decided before the appraisal is run, not discovered at the end of it. It has to cover the risk being taken, the time the money is tied up, and whatever return the equity has been promised. If the scheme is funded, the lender will have its own view of the minimum margin it wants to see and will test the appraisal against it.

Treating profit as the residual instead of the land value is the single most common way an investor talks themselves into a bad site. The land price becomes fixed, the profit absorbs every cost increase, and by the time the scheme is on site there is nothing left to absorb anything.

Finance cost follows the programme

Interest accrues on what is drawn, for as long as it is drawn. That makes the cost of finance a function of the programme, and the programme a function of the design, the planning route and the procurement route. A scheme that takes six months longer than assumed does not just cost six months of interest. It also carries six months of preliminaries, inflation on unlet packages and a sales period that may have shifted into a different market.

Arrangement, exit and monitoring charges belong in the same section of the appraisal. The detail varies between lenders, so the figures need to come from the facility being discussed rather than from a previous deal. We set out what funders look for in funding preparation.

Test the number before you bid

A single residual figure is not an answer, it is one outcome. The useful work is the sensitivity test: what happens to the land value if build cost rises, if sales values fall, if the programme stretches, if the planning consent comes with obligations you had not allowed for. As an example only, a scheme that stops working when build cost rises by a few per cent is not a scheme with a tight margin, it is a scheme with no margin at all.

That test also tells you what to negotiate. If the residual is sensitive to the planning outcome, the answer may be a conditional contract rather than a lower price. If it is sensitive to ground conditions, the answer is an investigation before exchange rather than an allowance after it. The risks worth checking before you commit are set out in seven site risks to check before you exchange.

Measurement underpins all of it. Where a scheme is close to the line, the difference between a rate and a measured quantity is the difference between a decision and a guess, which is why quantities and take-off work earns its place even at appraisal stage. Carrying that same set of numbers through planning, funding and the build is what development management is for.

Running the numbers on a site you are considering?

We build the appraisal from measured cost, test it against the sales evidence and tell you the price at which the scheme stops working.

Related